image_pdfimage_print
✓ Draft saved
Commissioning record — progress 0%
P1
2a
2b
3a
3b
3c
Approved Document F, Volume 1 — Appendix C

Completion Checklist & Commissioning Sheet

Complete on site. Parts 3a / 3b / 3c — fill whichever applies to the installed system.

Regulatory Edition
Required
Select the edition of ADF(1) governing this project. Determines the declaration on the output record.
Part 1 — System Details & Declarations
Required
All fields marked * are required for Building Control submission.

1.1 — Installation Address

1.2 — System Classification

Units / Systems Installed

Select the VENTI product from the dropdown. Add as many units as required.

1.3 — Installation Engineer

1.4 — Commissioning Engineer

Dwelling Parameters — Whole-Dwelling Ventilation Check

ADF(1) para 1.20: The minimum whole-dwelling ventilation rate is the higher of the bedroom-count rate (Table 1.3) and the floor-area rate (0.3 l/s/m²). Both calculations are applied and the larger value governs.
Part 2a — Installation Details
Required — all systems
Complete before commissioning begins.
Installation checkResponse
Installed per manufacturer's requirements??
ADF(1) paragraphs 1.74–1.87 followed (ducting, insulation, terminals, inspection)??
Any deviations from paragraphs 1.74–1.87 — documented?
Part 2b — Visual Inspection (Pre-Commissioning)
Required — all systems
Complete before Part 3.
Inspection item — all systemsResponse
Background ventilator quantity and equivalent area meets ADF(1) (Table 1.7 natural vent.; para 1.64 continuous MEV)??
All background ventilators left in open position?
Correct number and location of extract terminals — satisfy Table 1.1 or 1.2?
Installation complete — no obvious defects?
Internal doors have sufficient undercut — 10mm above floor finish or 20mm above bare floor surface (para 1.21)??
All protective packaging removed (including from background ventilators)?
All systems clean internally and externally?
System installed to allow maintenance access and component replacement?

2b.3 — Other inspections

CheckResponse
At initial start-up: any abnormal sound, vibration or unusual smell?
During continuous operation: any excessive noise?

Ducted systems — continuous MEV / MVHR additional checks

Required for Part 3b and Part 3c systems. Leave blank for natural ventilation (Part 3a).
Additional inspection item — ducted systemsResponse
Appropriate air terminal devices installed to allow system balance?
Heat recovery unit and all ductwork effectively insulated and sealed — heated and unheated spaces?
Condensate connection complete and draining correctly? (MVHR / srMVHR only)
Filters installed?
Ductwork installed to minimise air resistance and leakage?
Part 3a — Intermittent Extract Fan Testing
System 1 — Natural ventilation
Complete this section for natural ventilation with intermittent extract fans (System 1). Leave blank if not applicable.

3a.1 — Commissioning Equipment (UKAS calibrated)

Requirement: Device and hood calibrated together within 12 months at a UKAS-accredited centre. Accuracy ±5%. Range must include at least 4 l/s through maximum design rate.
Device model & serial numberUKAS calibration dateCertificate no.

3a.2 — Airflow Measurements

ADF(1) Table 1.1 minimum rates shown as reference. Enter design rate and measured rate. Pass = measured ≥ design rate. Measured rate = average over ≥10 seconds.
Room type ADF(1) min. (l/s) Design rate (l/s) Measured (l/s) Status

For cooker hoods, record highest setting only.

Part 3b — dMEV Commissioning (Decentralised Continuous Extract)
System 3 decentralised — dMEV
Complete for decentralised continuous extract (dMEV — no heat recovery). Leave blank if not applicable.

3b.1 — Commissioning Equipment (UKAS calibrated)

Device model & serial numberUKAS calibration dateCertificate no.

3b.2 — Airflow Measurements (Extract)

High rates from ADF(1) Table 1.2. Total continuous rate of all units must meet the whole-dwelling rate (Table 1.3, calculated from bedroom count and floor area above).
Room type ADF(1) high rate min. Measured high rate (l/s) Status Measured continuous (l/s)
Total continuous rate (all units) → whole-dwelling 0.00 l/s
Part 3c — Centralised MEV / MVHR / srMVHR Commissioning
Systems 3 & 4 — centralised / heat recovery
Complete for centralised MEV or any MVHR / srMVHR / dMVHR system. Supply section (3c.3) is required for heat recovery systems only — leave blank for extract-only systems.

3c.1 — Commissioning Equipment (UKAS calibrated)

Device model & serial numberUKAS calibration dateCertificate no.

3c.2 — Extract Airflow Measurements

Room type ADF(1) min. high rate (l/s) Design high rate (l/s) Measured high rate (l/s) Status Design continuous (l/s) Measured continuous (l/s)
Total extract continuous rate → whole-dwelling 0.00 l/s

3c.3 — Supply Airflow Measurements (MVHR / srMVHR only — leave blank for MEV / dMEV)

Room type Design high rate (l/s) Measured high rate (l/s) Design continuous (l/s) Measured continuous (l/s)
Total supply continuous 0.00 l/s
VENTI Appendix C Commissioning Tool v1.3.0 — ADF(1) 2021 & 2026

Approved Document F — Appendix C Commissioning Record

Generated by VENTI Commissioning Tool v1.3.0

Last Updated on 28 April 2026 by Bradley Pallister

Like this:

0